In the field of industrial equipment maintenance, the EPC (Engineering, Procurement, and Construction) model has emerged as a strategic solution for companies seeking to reduce costs and improve efficiency. Leveraging the integrated advantages of design, procurement, and construction, LEFILTER’s EPC project team recently completed a high-standard filter media replacement project for a 1250 high-speed filter in a steel rolling mill — setting a new benchmark in industrial maintenance services.
Project Background and Technical Challenges
The 1250 high-speed filter is a critical component of the steel plant's water treatment system. As the filter media aged, system efficiency declined, prompting the need for a professional upgrade. LEFILTER's EPC team stepped in with a comprehensive plan tailored to meet several technical challenges:
Precision Requirements: Each filter unit required the replacement of 580 filter nozzles and layered filling of quartz sand (4-8mm, height 1m) and anthracite (4-8mm, height 1.2m), demanding exact execution.
Multilateral Coordination: The project involved strict division of responsibilities between the plant and construction team, including acceptance of removed media and quality verification of new materials.
Green Construction Standards: Disposal of used media required full protection during transport to prevent environmental contamination while ensuring a swift equipment restart.
Full-Process Advantages of the EPC Model
1. Technical Design and Execution
Customized Design: Based on processing capacity (385 m³/h) and filtration area (9.62 m²), the team developed a precise filter media loading plan to ensure optimal efficiency and flow rate.
Strict Quality Control: All materials, including filter nozzles and quartz sand, came with quality certifications and passed random inspection by the plant.
Step-by-Step Acceptance: Old media was cleared and confirmed as residue-free, and new media was validated through water flow tests to ensure stable performance.
2. Efficient Construction Management
Clear Role Assignment: The plant provided utilities and base materials, while LEFILTER supplied tools, replaced filter nozzles, and handled end-to-end construction.
Eco-Friendly Operations: A professional team handled the used media, with dust-proof covers during transport and full cleanup post-construction.
On-Site Supervision: Key processes, including layered media filling and system flushing, were monitored closely to guarantee safety and accuracy.
3. Core EPC Benefits: Reliability and Speed
20% Shorter Timeline: With integrated planning and fewer communication gaps between departments, LEFILTER significantly accelerated project completion.
Efficient Resource Integration: The team used in-house tools and components, reducing the burden on the plant's logistics.
End-to-End Assurance: LEFILTER took full responsibility for test-run outcomes, ensuring smooth equipment restart and minimal downtime.
Through technological innovation and refined project management, LEFILTER's EPC team delivered a high-performance, environmentally responsible solution for industrial filtration maintenance. The successful completion of the steel plant project reflects not only technical excellence but also seamless team collaboration and strong commitment to sustainability.
RELATED NEWS
How to maintain the multi cartridges self-cleaning filter?
2023-05-04
Multimedia Filter: A New Tool for Environmental Protection, Protecting Water Resources
2024-09-04
Which industries are automatic slag discharge filters used in?
2023-04-04
Shallow Sand Filter: Key Compliance Factors in Wastewater Treatment Regulations
2024-10-28